Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.
in "Dancing Widgets" for the upcoming Christmas season. You've been informed that the company needs at least one month lead time to distribute the Widgets in order to have the Widgets on retailers shelves for the Christmas season. Hence, based on the current sales forecast you have been asked to deliver, units by august1st at the latest. Which document describes the business needs for this project, identifies key deliverables, and gives you authority to begin the project and start assigning resources? A. RFQ B. None of the choices are correct C. Ishikawa document D. RFP E. WBS
Yes, If this is related to work, It is not only getting certification and Exam.
Thank you
B. None of the choices are correct