Communiquez avec les autres et partagez vos connaissances professionnelles

Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.

Suivre

You are in the process of analyzing activity sequence, durations, resource requirement, and schedule constraints in order to c?

reate the project schedule. Which of the following is least helpful input in this process? A. Activity duration estimates, risk register B. Project scope statements, activity list C. Schedule baseline, performance reports D. Activity resource requirement, resource calendars E. Activity attributes, project schedule network diagram

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2019/04/04
Muhammad Farooq
par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

C. Schedule baseline, performance reports 

More Questions Like This