Communiquez avec les autres et partagez vos connaissances professionnelles

Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.

Suivre

You are in the process of developing an approximation of the costs of the resources needed to complete each schedule activity. ?

Which of the following statements are FALSE regarding this process? A. None of the choices are correct B. Schedule activity duration estimates may affect cost estimates that have time-sensitive costs C. Activity duration estimating will affect cost estimates when the project budget includes an allowance for cost financing D. The staffing management plan is an input to this process and describes the type and quantity of resources required to complete project work E. Activity resource estimation involves determining the quantity and type of resources required (staff, equipment, material, etc) and is loosely coordinated with the cost estimating

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2019/04/11
Muhammad Farooq
par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

D. The staffing management plan is an input to this process and describes the type and quantity of resources required to complete project work