You are involved in monitoring specific project results to determine whether they comply with relevant quality standards. ?

You are using a control chart to illustrate how a process is behaving over time. You've constructed your control chart and determined that all the data points are within the upper and lower control limits of the chart. In addition, seven consecutive data points are observed to be on the one side of the mean. Which of the following is your BEST plan of action? A. Compare the results from the lat quality management plan B. No additional action is needed, as the process is within control C. Adjust the mean based on the observed data points D. Identify the assignable causes

user-image
Question ajoutée par Muhammad Farooq , QA-QC Manager , AL Bawani Contracting Co
Date de publication: 2019/04/11
Ayman Hilmy
par Ayman Hilmy , LEAD SITE ENGINEER , MASAH

The answer is B no additional action is needed

Muhammad Farooq
par Muhammad Farooq , QA-QC Manager , AL Bawani Contracting Co

D. Identify the assignable causes  ------------