You are the project manger at a construction company. Your company is currently in the process of developing a-unit apartment complex. ?

Your company plans to subcontract all the electrical wiring of the building to an outside vendor. The subcontractor's work will involve wiring the building for electrical power, as well as cable and Internet Ethernet wiring. In which of the following processes will a contract between the buyer and seller be created? A. Plan contracting B. Plan purchases and acquisitions C. Request seller responses D. Contract administration E. Select sellers

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2019/04/11
khalid khan
par khalid khan , HR Operations Specialist , INFRAROAD Trading & Contracting

D. Cobtract Administration

Jyothsna Vidavaluru
par Jyothsna Vidavaluru , Project Manager, Scrum Master, Agile Coach , Larsen & Toubro Infotech Limited

In general

A. Plan Contracting is done at Buyer's end

B. Plan Purchases and Acquisitions also done at Buyer's end

C. Request seller response - eventhough seller responds, initially done by buyer

D. Contractor Administration - Includes all the processes related to procurements, inviting for bidding, negotiation, selecting seller, awarding contract...... which are done mutually by both seller and buyer

E. Select seller - Also done by buyer

So, according to me too, answer should be   D

Abdullah Alkharaan
par Abdullah Alkharaan , Deputy Branch Manager , Strukton Civiel Projecten BV, Saudi Arabia

I would go with D- Contract administration

Sir,

A. Plan contracting is the answer.

Muhammad Farooq
par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

E. Select sellers -------------------