Which of the following is the BEST candidate for a three-point estimate?

A. A brief schedule activity that takes a couple of hours B. A schedule activity with a considerable variation C. A schedule activity with a fixed duration D. A schedule activity with little duration variation

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2019/04/17
Muhammad Farooq
par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

B. A schedule activity with a considerable variation