alternative forms of energy. You have just completed the project Scope Planning process and created the Scope management plan. However, upon review, you have determined that the resulting project scope management plan is ambiguous and poorly written. A poorly written project scope management plan will directly impact all of the following EXCEPT: A. Ability to identify the necessary activities that needs to be performed to produce project deliverables B. Ability to control changes to the project scope C. Ability to create a detailed project scope statement as the basis for future project decisions. D. Ability to formalize acceptance of the project deliverables E. Ability to define, prepare and integrate, all subsidiary plan, into the project management plan
Scope should be clearly stated for exact identification of works to be done.
E. Ability to define, prepare and integrate, all subsidiary plan, into the project man