You are the project manager at a utility company. Due to the recent rise in the cost of petroleum, your organization is exploring cheaper, ?

alternative forms of energy. You have just completed the project scope changes, requested changes, and updates to the project scope management plan. Which of the following process did you just complete? A. Develop preliminary project scope statement B. Scope definition C. Scope planning D. Scope verification E. Develop project management plan

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2019/05/08
Arief Budhiarto
par Arief Budhiarto , Account Executive Officer , PT CIKARANG LISTRINDO, TBK

D. Scope verification, in order to make the very good plan

Haiam Al -Uaimer
par Haiam Al -Uaimer , Accounts Director , Almond

As the project manager at a utility company facing higher petroleum costs, the organization is actively exploring cheaper and more sustainable energy alternatives. Key strategies include investing in renewable energy sources like solar, wind, hydro, and geothermal power, implementing energy efficiency initiatives, deploying smart grid technology, and promoting demand response programs. Energy storage solutions, diversification of energy sources, and securing long-term contracts are also considered to reduce vulnerability to petroleum price fluctuations. The utility company aims to optimize energy usage, lower operational expenses, and contribute to a greener and more sustainable energy future through these efforts.

Ihsan Idelby
par Ihsan Idelby , General Manager , Sanrock Hotel

  1. Scope verification

Explanation:

Scope verification is the process of formally accepting the completed project deliverables. In this scenario, since you have completed the project scope changes, requested changes, and updates to the project scope management plan, you are essentially ensuring that the scope has been correctly defined and agreed upon by the stakeholders.

Here's a brief overview of the other options:

  • A. Develop preliminary project scope statement: This is an earlier process where you define the initial scope of the project.
  • B. Scope definition: This process involves breaking down the project deliverables into smaller, more manageable components but doesn't necessarily involve verifying changes.
  • C. Scope planning: This process establishes the scope management plan, detailing how the project scope will be defined, validated, and controlled.
  • E. Develop project management plan: This encompasses integrating all aspects of the project, including scope, schedule, and cost, but does not specifically focus on verifying scope changes.

In summary, since you have completed scope changes and updates to the scope management plan, it indicates that you have gone through the Scope verification process to ensure that the changes align with the project objectives and are accepted by the relevant stakeholders.

Ashraf Alja'fari
par Ashraf Alja'fari , Integrated Shipping Manager , Amin Kawar And Sons Company

C.

The statement comes first along with the definition and verification + develop comes after the planning.

QUDRATH ALI MOHAMMED
par QUDRATH ALI MOHAMMED , Sales Executive , Airlink International UAE

 A. Develop preliminary project scope statement

Muhammad Farooq
par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

B. Scope definition -----------------

amjad iqbal
par amjad iqbal , Group Product Manager , Shaigan Pharmaceutical Pvt. Ltd Pakistan

A: Scope definition

B: Develop preliminary project scope statement

C.  Scope planning

D. Scope Management & verification

E. Develop project management plan

F: Project Managment & Human Resource Management