All of the following statements are true regarding the critical path method EXCEPT: ?

A. The critical path method performs a forward pass analysis and backward pass analysis through the project schedule network paths. B. Critical paths have either negative or zero total float C. On a network path, the schedule flexibility is measured by the difference between early and late dates D. The critical path method calculates the theoretical early start and finish dates for all schedule activities E. The critical path method accounts for resource limitations

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2019/06/19
andre andre
par andre andre , On Site Sitemanager/Structural /Civil/Mechanical/Tank plate Erection. , Kanye Kanye Projects Africa.

Critical path mesuerement used based on your Planning scope of work that are being carried out [Control System].

Dalia safey
par Dalia safey , nursing administration and staff development , Cairo University Hospitals

C. On a network path, the schedule flexibility is measured by the difference between early and late dates 

Athar Mohammed Khan
par Athar Mohammed Khan , Account Officer , The Kidney Ceentre Post Graduate Training Institute

The critical path method (CPM) is a project modeling technique.

E. The critical path method accounts for resource limitations 

akhtar bebal
par akhtar bebal , Chief accountant /credit controller , Coca-cola

The critical path method (CPM) is an algorithm for scheduling a set of project activities. The critical path method (CPM) is a project modeling technique developed in the late 1950s by Morgan R. Walker of DuPont and James E. Kelley, Jr. of Remington Rand. Kelley and Walker related their memories of the development of CPM i

 

 

 

 

 

 

 

Muhammad Farooq
par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

E. The critical path method accounts for resource limitations