In the payments terms for construction what is the supporting documents’ to be submitted to the account section to effect payment for the contractor ?

user-image
Question ajoutée par elfatih mohamed ali Ali , Procurement and Logistic Officer , Sudanese Microfinance Development Facility SMDF
Date de publication: 2013/11/21
Md Fazlur Rahman
par Md Fazlur Rahman , Procurement Specialist , Engineering and Planning Consultants Ltd

Normally, the documents to be submitted for payment are detailed in work order or purchase order. However, the following documents are necessary:

 

1.    Copy of contract document signed by the Purchaser as well as the contractor.

2.    Work completion certificate including MB (measurement book), individual item costing signed by the supervisor and the contractor and finally authorized by the designed official/Engineer

 

3.    A certificate from the contractor that work has been completed as per specification in the contract document and within the specified time frame in contract. This is to be certified by the supervisor of works and authorized official also.

Ahmed Takieddine BELKHIR
par Ahmed Takieddine BELKHIR , Architecte , The Arab Contractors

The documents of payments are called "Situations"