Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.
Every activities having some standard productivity. Eg., For Shuttering Work, 1Sqm of Shuttering works 0.75 Mandays required. Based on that we will prepare the Budgetted units of labor resource to each and every activity.Then How to analyze the actual productivity that we getting from this resources because man to man outcome of work will difference..
Hi,
I write an article regarding How to define Resource Productivity in Primavera P6 and create schedule.
If you're interested, kindly read it here https://doduykhuong.com/2017/03/27/how-to-define-resource-productivity-in-primavera-p6-and-create-schedule/
Make user defined columns for budgeted quantity , standard productivity,actual productivity
display columns for actual duration,actual labour units, Duration
make global change calculation for deriving actual productivity using above mentioned columns. then actual productivity can be obtained for all activities