Communiquez avec les autres et partagez vos connaissances professionnelles

Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.

Mohammed Awwad
par Mohammed Awwad , Senior Digital Consultant , BDO Jordan

It defines a logical closure of any deliverable or cycle.
Example you have completed the requirement phase with sign off from the client on the requirement document.So you put a baseline and say that further any changes to this document are change request.
Versioning of source code is one type of baseline.

Binil Paul
par Binil Paul , Sr. Planning Engineer , KEO International Consultants

A baseline is a complete copy of a project plan that yu can compare to the current schedule to evaluate progress.
The simplest baseline plan is a complete copy , or snapshot of the original schedule.
This snap shot provides a target against which you can track a projects cost, schedule and performance.

Utilisateur supprimé
par Utilisateur supprimé

A project Baseline is a point where the project is based from.
It usually represents the initial view of project timeframes and resources.
Once it is approved and kicks off is a typical time to baseline the project.
Any variations from baseline then, should have an explanation.
For example, there may be change requests, or a particular activity ran late.
Variations and their reasons are usually reported to the project board, and at the PIR a history of how the project varied from baseline will contribute to the learning database.

Tanveer Ahmad Niazi
par Tanveer Ahmad Niazi , CEO (Self-employed) , Project Management Training & Consultant

I am agree with Binil Paul Anisuddin Siddiqui and Hafiz syed only, please read and further explain my question “What are Program of Works, Clause14 Program and Baseline Program?in the specialty of project evaluation, project management or project planning.

Anisuddin Siddiqui
par Anisuddin Siddiqui , Sr. Planning Engineer , Southwest Architecture

A Project baseline is a snapshot of project after you complete it in all respect and got approval from authority but before you start updating it with actuals.
The baseline is then used afterwards to compare Project performance against baseline to assess the project progress and locate problem area.

Ammar Elmubarak, MBA, PMP, CSPO
par Ammar Elmubarak, MBA, PMP, CSPO , Senior Project/Requirements Manager , NASA

Per PMI, the project’s baseline consists of
1- The scope baseline that includes project scope statement, work breakdown structure and WBS dictionary.
2- The cost baseline which is a time-phased budget used in monitoring and measuring cost performance throughout project life cycle that includes a budget contingency to accommodate for risks.
3- The schedule baseline which is an approved snapshot of the project schedule.
All three baselines represents the project's baseline that is used to measure how the project deviates from the plan in meeting the project goals.

Hodan Ali
par Hodan Ali , HR manager , ME COURIER

In project management A project’s baseline is defined as the original scope, cost and schedule.
The project’s baseline must be completely defined and documented before the project execution and control activities can begin.
Time, cost and scope it the first plan of any project to success

Hafiz Syed Nazim Ali
par Hafiz Syed Nazim Ali , Project Co-ordinator , Radic Construction LLC

Project baseline is a project which is a bench mark to monitor the current progress of your project.
In some programs for planning and scheduling it is also termed as target project.
Any project before being fixed as a project baseline requires approval form all stake holders of the project.

Fawad Ali Awan
par Fawad Ali Awan , Senior HSE Officer , Arabtec Construction LLC

In project management, the baseline is the original range, total cost and schedule of a project. It is used to measure the amount of deviation of performance from the original plan. Before the execution of the project, the baseline must be properly defined and documented.

Abrar Hussain
par Abrar Hussain , Contract Manager , Sahara Tamiratt

Baseline Plan of any Project basically the agreed copy of proposed Project Plan from the begining to Completion or End of Project.

It provides help during execution to compare the current activity schedule / Plan and defines the standing of on going Project during various stages of Project Progress.

Georges Kaddoum
par Georges Kaddoum , Operations Manager , American University of Beirut - Medical Center

It simply defines the Planned duration of a project , setting a planned start and end date. These baselines are based on the estimations in terms of Project scopre as well as Resource availability. The benefit it is be able to track when we are by passing the planned periods , either before starting or while in progress and moving towards the Planned delivery date 

More Questions Like This