What should be documented while preparing OSP drawings for Telecom ducts and cables? What is important to be shown on the drawings before giving it to field staff for implementation?

user-image
Question ajoutée par Muhammad Naeem , Site Engineer , Huawei Tech
Date de publication: 2013/12/21
ABDUL RAZZACK VALIYAKATH
par ABDUL RAZZACK VALIYAKATH , Project Manager - OSP , AL HANOO CONTRACTING ( Telecom Division )

While preparing the OSP drawing for telecom cable and ducts it is necessary to collect the physical servery report of the perticular site including the existing underground utilities and services.

 

mohamed ibrahim shutta shutta
par mohamed ibrahim shutta shutta , osp eng specialisted in fiber optic , sudatel

Duct routes\\JBS(Manholes)/Subduct routes&labling/cable Labling/JBS labling\\accessories labling/GPs coordinates for JBS

kishore Annam Thyaga Raja kishore
par kishore Annam Thyaga Raja kishore , utl technologies , utl technologies

OUT SIDE PLANTS FOR OF NETWORKS DIFFER FOR WIRELESS NETWORKS AND BROADBAND DEPLOYMENTS; DEPLOYED RJIL INDIA, RCOM INDIA, BHARATNET GPON FTTX IN INDIA

Fayaz ahamed Showkath ali
par Fayaz ahamed Showkath ali , Project Engineer (OSP) , Goo Brothers Electrical Engineering Sdn Bhd

For design we need to survey the particular area.

Need to collect information about the number of existing customers, requirement for the future development etc.

 

Mahaboob Basha  syed
par Mahaboob Basha syed , Teamleader , Bechtel

ROW, duct/ cable routing, Manholes and HDD profiles in Cadd.

DF, AF and Drop cable routing. 

 

Douglas Charles Mawema
par Douglas Charles Mawema , General Electrician , Gold mine

OSP  DETAILS   YOU  MUST  HAVE BUYING  AND  SELLING  DATA

Sunil Patil - PMP
par Sunil Patil - PMP , GIS Consultant , Bin Omran Trading & Telecommunication

To design OSP you must have survey data such as the number of potential customers, type of customers, property type, civil infrastructures (Duct, Manholes, JOintboxes) etc. and of coarse you must have a base map to design the OSP network. based on this you can execute the OSP design

Mr. naeem you are right i want to talk with you this is my no 

TUHIN SANKAR SAR
par TUHIN SANKAR SAR , Operations and maintenance Engineer , Tata Communications Ltd.

Draw and provideeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeee

Samuel Colar
par Samuel Colar , CAD Designer , Consolidated Gulf Company

Cable Routing and Manhole Fold Out Drawings.

Harold Villar
par Harold Villar , Quality Manager , Sumitomo Corp[oration-Saudi Branch

Gather all the information data such as forecast report for number of potential customers growth including 10 years projection demand, perform the preliminary cabinet sizing & fundamentals to determine the demand requirements for secondary & primary cables. Then prepares cable trench, manholes & conduit layout, schematic cable diagram, manhole fold outs drawings that provides all details for executing in construction.