If you have a concrete raft 1600 m3 , and you dont have enough shuttering to cast it one time , what are your recommendations?

user-image
Question ajoutée par Mohamed Sulaiman , Site Project Manager , Al tabarak for Engineering & Contracting company
Date de publication: 2013/12/31
hassan amer ali algaifi
par hassan amer ali algaifi , مهندس مشروع , مؤسئسة علي الحصان للمقاولات

we have to find the best location for construction joint in raft foundition.

it means to avoid location near max moment.

also to provide key conncetion between concrete.

and  add reinforcement for shear.

 

OSAMA SAADAWI
par OSAMA SAADAWI , Senior Structural Design Engineer , Chemonics

U can either:

1. U must provide a construction joint where u trim the concrete @45 degree with bars protruding with       enough  anchorage length.

2. Buy extra wood to form a complete shuttering.

Abdussalam Ghanduri
par Abdussalam Ghanduri , General Manager , AL-MOHANDESS FOR CONSULTANCY

The matter should be thought about in relation to cost effective manner, and in relation to the project plan and time schedule. and do not forget the design engineer recomendations as risk avoidence for any changes. the solution could be constructon joints, sliding of forms to cover longer distance considering the concrete quality, it could be preparing for that by forming the sides in the ground it self. 

 

u need to stop pouring far of max moment places 

 

form the end of poured concrete @@ angle of45 

after the concrete is hardened  you should clean the inclined surface well and  apply some adebond to make sure that this area wouldn't be a weak point in the raft before you start pouring the new area  

Kidane Tesfaye
par Kidane Tesfaye , Project manager , GAD CONSTRUCTION PLC

I would break dawn the volume in to a managable size and use to cast it revolving the shutter depending the required curing period required for particular type of structure which we are intending to cast at a time.

MUHAMMAD SARFRAZ SHAMIM
par MUHAMMAD SARFRAZ SHAMIM , QA/QC & Technical Engineer at M/s. Cement Enterprises and Ready Mix LLC (CEMIX) , (Looking for Job Opportunity)

it is always recomended that the foundation should be poured at one time at any cost but some uncertinaty is always be there so, considering the facts of the uncertinity during cpnreting first plan to pour  foundation at one time or use proper and approperiate construction joint angling45 degree (slop / Trim) or follow the instruction of experts (Engineers at site).

 

Satish Bhone
par Satish Bhone , Engineering Consultants , L&T Infrastructure Engineering Ltd

It should be cast monolithically. Wait till you get full shuttering.

 

mohamed fouad
par mohamed fouad , Construction Manager , ABR

try to use block instat of shutter

Utilisateur supprimé
par Utilisateur supprimé

The last option i would do if really need to cast the whole quantity of concret  is to wait for the concrete that has been cast to quickly dry if its a hot day and slide the shutter  so the rest of the concrete is cast, although you have to keep the concrete in the truck wet while waiting for the casted concrete to dry either you put chemicals inside the truck to mix with concrete whilst waiting before you can slide the shutter and cast.....Its a risk thou!

Mohammed El Sayed
par Mohammed El Sayed , Project Manager , United Engineers

Refer to your consultant to determine the required design/location for construction joins.

Sohaib Ashraf
par Sohaib Ashraf , Resident Engineer , Meinhardt Pakistan pvt LTD

1. Provide Construction Joint Providing keys 