Communiquez avec les autres et partagez vos connaissances professionnelles

Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.

Suivre

What is the necessity of punch-list preparation?

Pre-commissioning equipment & system installation checking

user-image
Question ajoutée par Dipak Das Dipak , General Manager (M), Power , Tata Consulting Engineers Ltd
Date de publication: 2014/01/21
Tomas Gimenez
par Tomas Gimenez , Supervisor , Tepsi - Exterran

The necessity is to complete everything according to engineering, so with the preparation of a punch-list we have a document of what's missing, what's wrong and what we need to correct to have a ready for pre-commissioning and further a ready for commissioning.

Mudassar Bashir
par Mudassar Bashir , Process Safety Engineer , Saudi Aramco Total Refining And Petrochemical Company - Satorp

A gap analysis tool that enable us to identify the difference in physical installation with that of design. Also help in safe execution, control on project execution time, quality of work and a best tool for the orientation and understanding of the people with the plant

Mohammed Ahmed Loghbi
par Mohammed Ahmed Loghbi , Raw Material Administrator , Saudi Basic Industries Corporation (SABIC)

Final contractor payment is made when the punch list of items are completed to meet the project design required by the contract.

More Questions Like This