START TO START WITH SAME DURATION
FINSH TO FINSH
ALL LEED TO critical paths
it is very easy from msproject only push a button to find the crtical path
The Longest Duration Path will give you the information for the critical Path. Draw the network diagram and calculate the longest path. The longest Path with max duration will give you the critical path.
Perform forward pass analysis and backword pass analysis to identify the tasks with0 float. The critical path is composed of the consequtive tasks with0 float.