A conservative estimate profit of A Contractor complete his contract work 90 % .

Total Expenditure to date450, Estimate further expenditure to complete the contract including contingency250, Contract Price6120, work Certified550800, work UN-certified340 , cash received440640. Give your recommendation how much profit to be taken in profit and loss. a/c for the proportion of profit.