Communiquez avec les autres et partagez vos connaissances professionnelles

Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.

Suivre

How will you handle the risk of project cancellation?

What if clients want you to start project ASAP without signing the contract since contracts take1-3 weeks for legal reveiw & approval while project needs to be started ASAP

user-image
Question ajoutée par Rizwan Mirza , IT Project Manager / Agile Scrum Master , UnitedHealth Group (UHG)
Date de publication: 2014/04/05
AmanUllah PMP®
par AmanUllah PMP® , Project Engineer , Technical and Industrial Services Co.

well it depends on situation. if you are sure that the contract will be signed , then you can start critical activities... but if the contract approval is not sure one should not start and should convince the client on his point.

Osama Zaki
par Osama Zaki , Lead Planning Engineer , Archirodon

using the risk transfer:

(top management decision / escalation) OR (hiring subcontractor & using the same conditions)

More Questions Like This

Avez-vous besoin d'aide pour créer un CV ayant les mots-clés recherchés par les employeurs?