The detailed project scope statement includes all of the following EXCPET ?

A. Project objectives, project scope description, project requirements B. Fund limitation, cost estimate, configuration management requirements C. Project specification, approval requirements, WBS D. Project boundaries, project deliverables, project acceptance criteria E. Constraints/ assumptions, initial defined risks, schedule milestones

user-image
Question ajoutée par Mohamed El Sayed , Project Manager , Saudi Post
Date de publication: 2014/04/29
Fredy Makram Labib
par Fredy Makram Labib , R&D manager , Universal for home appliances

B

Ramy Zakher
par Ramy Zakher , Executive director , EEP

The detailed project scope statement not include .

 

B. Fund limitation, cost estimate, configuration management requirements.

Utilisateur supprimé
par Utilisateur supprimé

B

Elsayed Abdel Monem Sayed Abdel Halim  PMP
par Elsayed Abdel Monem Sayed Abdel Halim PMP , Projects Manager , Almenah for engineering contacting

B. Fund limitation, cost estimate, configuration management requirements 

Salauddin Mohammad
par Salauddin Mohammad , Sr. Manager, Software Development , Aspen Technology Inc

Answer is "B".

Mohammad Aslam
par Mohammad Aslam , Projects Manager , National Aluminium & Steel Factory

Those who has opted option "B", could you pls define Scope?

ARUN BENADICK
par ARUN BENADICK , Planning /Scheduling Engineer ( Ksa ) , Eastern Trading & Contracting Company

B. Fund limitation, cost estimate, configuration management requirements 

 

1.Fund limitation, cost estimation will be available in Bills of Quantities.

2.Management requirements will be internal documents. 

A. It provides guidance on how project scope will be defined, documented, managed, and controlled.B. It provides guidance on how project scope will be verified.C. It may be formal or informal, highly detailed, or broadly framed, based upon the needs of the project.D. It is separate from the project management plan.

Basem Nofal
par Basem Nofal , Manager - Technical and Construction , consolidated Contractors international company - Qatar

the most accurate answer is "B ". I do agree with Mr "khairy" that WBS creation comes right after creating the project scope statement

Elias Assaf
par Elias Assaf , Projects Manager , Private Engineering Office

b

Radar Abdulaziz
par Radar Abdulaziz , field engineer , GE Oil & Gas

B. Fund limitation, cost estimate, geometry management specification