Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.
A. Project objectives, project scope description, project requirements B. Fund limitation, cost estimate, configuration management requirements C. Project specification, approval requirements, WBS D. Project boundaries, project deliverables, project acceptance criteria E. Constraints/ assumptions, initial defined risks, schedule milestones
The detailed project scope statement not include .
B. Fund limitation, cost estimate, configuration management requirements.
B. Fund limitation, cost estimate, configuration management requirements
Those who has opted option "B", could you pls define Scope?
B. Fund limitation, cost estimate, configuration management requirements
1.Fund limitation, cost estimation will be available in Bills of Quantities.
2.Management requirements will be internal documents.
A. It provides guidance on how project scope will be defined, documented, managed, and controlled.B. It provides guidance on how project scope will be verified.C. It may be formal or informal, highly detailed, or broadly framed, based upon the needs of the project.D. It is separate from the project management plan.
the most accurate answer is "B ". I do agree with Mr "khairy" that WBS creation comes right after creating the project scope statement
b
B. Fund limitation, cost estimate, geometry management specification