Ali Harin , General Manager , Harinco For Contracting And Trading Company
In Microsoft Project the distribution of the cash flow over the time intervals will be a constant value but in Primavera P6 you can distribute the cash flow by variable amounts over the time intervals which will be close to the actual fund needed for the activities.