what is the difference between the flexible budget and static budget ?

user-image
Question ajoutée par Utilisateur supprimé
Date de publication: 2013/06/16
Mahran Al-Qadi
par Mahran Al-Qadi , Accountant , Ministry of Education

FLEXIBLE BUDGET YOU CAN DO RIVISION BETWEEN LINES BUT IN STATIC YOU CANT 

Idris Yassein Zubair
par Idris Yassein Zubair , Fixed Assets Controler , Suns of Suliman H.ALSaif for transport

Flexible budget prepared based on the acual quantative output to determine the price variances from the static budget.

Muhammad Sohail Anwar
par Muhammad Sohail Anwar , Finance Manager , The Food Concepts

Static budget is set one time for the full year and compared to the actual result till the end of period (say year)

Flexible budget is the one which consider the changing in budget according to the actual results say after each quarter next quarter can be adjusted according to the actual results .

Divyesh Patel
par Divyesh Patel , Assistant Professional Officer- Treasury , City Of Cape Town

Following are the main differences between static and flexible budget:

 

1. Nature

A static budget does not change with the actual volume of the output achieved. A flexible budget is designed to change appropriately with the level of activity attained. 

 

2. Scope

A static budget cannot ascertain costs correctly in case of any change in circumstances. Flexible budget can easily ascertain costs in different levels of activities.

 

3. Determination Of Cost

Static budget is prepared under the assumption that all conditions will remain unaltered. Flexible budget is prepared at different levels of activities considering the possible changes in the operational aspect of a business. 

 

4. Assumptions

Static budget has a limited application and is ineffective as a tool for cost control. Flexible budget has a wide application as an effective tool for cost control.

 

5. Pre-requisites

Static budget is prepared without classifying the costs according to their variable nature. Flexible budget is prepared by classifying the costs according to their variable nature.

munir mohsin
par munir mohsin , Managing Director , Pakistan Ordnance Factories

Flexible budget accounts for the flexibility of expenditure in various heads of expendidures allowing the reallocation whereas static budget does not allow this reallocation.As a principle flexible budget helps in adjustment of expenses in static budget.