For Ordinary Portland cement concrete exposed to dry and hot weather conditions, good moist curing period is how many days?

user-image
Question ajoutée par Almarozette Malinao Calamba , QA/QC ASSISTANT , YTC/ DAELIM INDUSTRIAL CO. LTD., KUWAIT
Date de publication: 2014/05/19
Mahmoud Abdulkader    Darwish
par Mahmoud Abdulkader Darwish , Consultant Bridge Engineer , Brench IDS consulting company

IT IS PREFERABLE  BETWEEN (10 -14 ) DAYS  THAT IS DEPENDING ON STRUCTURAL MEMBER

hatem labib
par hatem labib , Quality control manager , MISER consultant

14 days in most international specifications

Tamal Das
par Tamal Das , Assistant Resident Engineer , Keo International Consultants - Qatar

14 days (depending upon part of Structure)

THOMAS ATHAPPILLY
par THOMAS ATHAPPILLY , Construction Manager , Rajagiri Health and Education Trust, Alwaye - Kochi

To almost all international specifications say it is7days curing. I suppose this must be true in this case also. Unless there is any repairs carried out which again needs this7 days curing, for all practical purposes and to the specifications, the requirement is only7 days curing period.

 

But I would be surprised to know if there is any clear - cut procedure or guidelines exist anywhere if the specified curing period is not complied with by the Contractor. After documentation to this effect from the side of PMC, Client or Consultant, is there any specific guideline or recommended procedure to reduce the payable rate towards the Contractor due to the sub standard work performed by him?

Devesh Kr Trehan
par Devesh Kr Trehan , Project Manager , Rely Btl Production & Services

In the weather conditions as specified by you gentle moist curing must be extended to days. I prefer to continue curing even as work progresses for at least2 to4 days extra. 

Yasmine ElDahshoury
par Yasmine ElDahshoury , Structural Engineering , QDVC

14 days depends  upon structure

It's depends on type of structure Mosley7days(a week)

suhaib usmani
par suhaib usmani , Senior QA/QC Engineer , Qatar Building Company

varying10 -14 days, better to check specs in your location