Which of the following can be used to determine what work is included in each work package for each of your team members?

A. None of the choices are correct B. WBS dictionary C. RBS D. Project scope statement E. Project schedule

user-image
Question ajoutée par Ghassan Jaradat , Projects Manager , ITAC Information Technology and Automation Company
Date de publication: 2014/05/20
ABU SAIF MOHAMMAD MAHIN, PMP
par ABU SAIF MOHAMMAD MAHIN, PMP , Head of Design and Production Engineering, Financials Solutions , Southtech Limited

B. WBS dictionary 