Communiquez avec les autres et partagez vos connaissances professionnelles

Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.

Suivre

Is Start to finish relationship ever used in scheduling? Can you provide me with examples?

user-image
Question ajoutée par Ghada Sameer , Project Manager and media executive , CQA
Date de publication: 2014/05/28
Mohammed Thiab
par Mohammed Thiab , Founder / Chief Consultant , MV Consulting

Start-to-finish occurs when “the completion of the successor activity depends on the initiation of the predecessor activity,” or, said so that normal folks can process it: Activity A must start before Activity B can finish.

 

The most common examples are those associated with replacement of an old system by a new one as in the case of upgrades, replacements, obsolencence, ...  etc

 

In these case ...  activity A (the retirement of the old system) can NOT start until activity B (preparation of the new system to replace the old one) has already been finished !!

More Questions Like This

Avez-vous besoin d'aide pour créer un CV ayant les mots-clés recherchés par les employeurs?