Ask the Community
Ask any professional question and get answers from other specialists.
Time extension Concurrent delay analysis
Check with the insurance companies about the procedure regarding how to obtain exemption and dispensation in ad hoc and one off cases?
Concurrent delays can easily be defined as simultaneous delays caused by the general contractor and the project owner, affecting the project schedule and project completi ... See More
If your client reject the concurrent delay claim, he can ground his decision on lack of notice of delay from the contractor, informal notices of claim as stated in the co ... See More
first of all the contractor shall prove by documents that the delay is not his responsibility and that can be achevied by (contract documents and the contractor submittal ... See More
Explain with the best reason the need for the application of this procedure
The client needs no reimbursement.