Which of the following statements are true?‎

A. Procurement audits review the procurement process from plan contracting to contract closure B. Procurement audits review the procurement process from plan purchases a‎ ... Voir Plus

Réponses:
0
Adeptes:
Vues:
155
Vote Count:
0
La réponse doit contenir un minimum de 25 caractères.
Muhammad Farooq's image
La question a été ajoutée par Muhammad Farooq QA-QC MANAGER AL Bawani contracting co.
Depuis 8 années

Which of the following statements are true?‎

A. Procurement audits review the procurement process from plan contracting to contract closure B. Procurement audits review the procurement process from plan purchases a‎ ... Voir Plus

Réponses:
0
Adeptes:
Vues:
143
Vote Count:
0
La réponse doit contenir un minimum de 25 caractères.
Muhammad Farooq's image
La question a été ajoutée par Muhammad Farooq QA-QC MANAGER AL Bawani contracting co.
Depuis 8 années

Which of the following establishes the procedures to transfer the project product or services to production and / or operations?‎

  A. Contract closure procedure B. Administrative closure procedure C. Formal acceptance documentation D. Project files  ‎

Réponses:
2
Adeptes:
Vues:
176
Vote Count:
0
La réponse doit contenir un minimum de 25 caractères.
Muhammad Farooq's image
La question a été ajoutée par Muhammad Farooq QA-QC MANAGER AL Bawani contracting co.
Depuis 8 années

You are in the contract Closure process and are reviewing the contract process to identify the lessons learned. Which of the following best describes?‎

the tool/technique you are using? A. Procurement audits B. Procurement reports C. Procurement reviews D. Performance audits E. Performance reviews‎

Réponses:
3
Adeptes:
Vues:
361
Vote Count:
0
La réponse doit contenir un minimum de 25 caractères.
Muhammad Farooq's image
La question a été ajoutée par Muhammad Farooq QA-QC MANAGER AL Bawani contracting co.
Depuis 8 années

All of the following are outputs the closure project process EXCEPT:‎

  A. Contract closure procedure B. Administrative closure procedure C. Final product, service or result D. Work performance information E. Historical infor‎ ... Voir Plus

Réponses:
0
Adeptes:
Vues:
69
Vote Count:
0
La réponse doit contenir un minimum de 25 caractères.
Muhammad Farooq's image
La question a été ajoutée par Muhammad Farooq QA-QC MANAGER AL Bawani contracting co.
Depuis 8 années

Contract documentation is an input to the Contract Closure Process. It includes all of the following EXCEPT:‎

  A. Approved changes requests B. Warranties C. Technical documentation D. Supporting schedules E. Contract closure procedure‎

Réponses:
0
Adeptes:
Vues:
56
Vote Count:
0
La réponse doit contenir un minimum de 25 caractères.
Muhammad Farooq's image
La question a été ajoutée par Muhammad Farooq QA-QC MANAGER AL Bawani contracting co.
Depuis 8 années

Contract documentation is an input to the Contract Closure Process. It includes all of the following EXCEPT:‎

  A. Approved changes requests B. Warranties C. Technical documentation D. Supporting schedules E. Contract closure procedure‎

Réponses:
0
Adeptes:
Vues:
45
Vote Count:
0
La réponse doit contenir un minimum de 25 caractères.
Muhammad Farooq's image
La question a été ajoutée par Muhammad Farooq QA-QC MANAGER AL Bawani contracting co.
Depuis 8 années

Contract documentation is an input to the Contract Closure process. It includes all of the following EXCEPT:?‎

  A. Approved change requests B. Supporting schedule C. Procurement audit documentation D. Warranties E. Payment records‎

Réponses:
0
Adeptes:
Vues:
35
Vote Count:
0
La réponse doit contenir un minimum de 25 caractères.
Muhammad Farooq's image
La question a été ajoutée par Muhammad Farooq QA-QC MANAGER AL Bawani contracting co.
Depuis 7 années

You are a project manager for Dutch Harbor Consulting. Your latest project involves the upgrade of an organization's operating system on 236 servers?‎

You performed this project under contract. You are in the Contract Closure process and have reviewed the contracting process to identify lessons learned. What is the name‎ ... Voir Plus