La question a été ajoutée par Muhammad Farooq QA-QC MANAGER AL Bawani contracting co.
Depuis 6 années

You're managing a project with a schedule performance index (SPI) of 1.07 and a cost performance index (CPI) of 0.94.?‎

How would you BEST describe this project? A. The project is behind schedule and over its budget B. The project is ahead of schedule and within its budget C. The project i‎ ... Voir Plus

Réponses:
1
Adeptes:
Vues:
343
Vote Count:
0
La réponse doit contenir un minimum de 25 caractères.
Muhammad Farooq's image
La question a été ajoutée par Muhammad Farooq QA-QC MANAGER AL Bawani contracting co.
Depuis 6 années

Post mortem Earned value analysis of a project which is going to be closed showed the following data: SPI: 0.72, CPI: 1.00, What is this telling you? ‎

A. The entire work of the project has been finished behind schedule and on budget. B. The entire work of the project has been finished ahead of schedule and on budget. C.‎ ... Voir Plus

Réponses:
6
Adeptes:
Vues:
19
Vote Count:
0
La réponse doit contenir un minimum de 25 caractères.
Mohammed Ayanuddin's image
La question a été ajoutée par Mohammed Ayanuddin
Depuis 1 an
Réponses:
1
Adeptes:
Vues:
1
Vote Count:
0
La réponse doit contenir un minimum de 25 caractères.
Bakht Rawan's image
La question a été ajoutée par Bakht Rawan Engineering (Q.S/Estimator) MECHANICAL/STEEL STRUCTURE/MEP/PIPING/CIVIL Najran Company KSA now and DESCON + Heavy Mechanical Complex (HMC) Pakistan previous
Depuis 11 années

How to resolve the Project site disputed matters to clear the bills or invoices/IPCs etc.?‎

When Interim Payment Certificates (IPC) is required to clear from either Client or Sub-contractor for billing.‎

Réponses:
0
Adeptes:
Vues:
30
Vote Count:
1
La réponse doit contenir un minimum de 25 caractères.
Helal Elsaadi's image
La question a été ajoutée par Helal Elsaadi Director– Projects Planning & Controls ROSHN Real Estate Company
Depuis 7 années
Réponses:
0
Adeptes:
Vues:
4
Vote Count:
0
La réponse doit contenir un minimum de 25 caractères.
Muhammad Farooq's image
La question a été ajoutée par Muhammad Farooq QA-QC MANAGER AL Bawani contracting co.
Depuis 6 années

You're managing a project with a schedule performance index (SPI) of 1.07 and a cost performance index (CPI) of 0.94. ?‎

How would you BEST describe this project? A. The project is behind schedule and over its budget B. The project is ahead of schedule and within its budget C. The project i‎ ... Voir Plus

Réponses:
2
Adeptes:
Vues:
3
Vote Count:
0
La réponse doit contenir un minimum de 25 caractères.
Default profile image
La question a été ajoutée par Abhijeet Singh
Depuis 6 années
Réponses:
0
Adeptes:
Vues:
0
Vote Count:
0
La réponse doit contenir un minimum de 25 caractères.
Muhammad Farooq's image
La question a été ajoutée par Muhammad Farooq QA-QC MANAGER AL Bawani contracting co.
Depuis 6 années

Post-mortem analysis of a project shows a CPI of 0.8 and an SPI of 1.25. What is a plausible explanation for that? ‎

A. The project has evidently been finished over budget and ahead of schedule. B. The project has produced additional deliverables which were originally not required. C. T‎ ... Voir Plus

Réponses:
1
Adeptes:
Vues:
1
Vote Count:
0
La réponse doit contenir un minimum de 25 caractères.
Muhammad Farooq's image  
La répondre a été ajoutée par  Muhammad Farooq, QA-QC MANAGER, AL Bawani contracting co.
Depuis 6 années

D. The project has been terminated before completion. At that time it was behind schedule and on budget