Discussions Populaires Dans la Communauté Gestion de la valeur gagné

S'abonner

Questionnez la Communauté


Ask any professional question and get answers from other specialists.

Stream language
ZULFIQAR ALI's image
La question a été ajoutée par ZULFIQAR ALI Planning/ Project Control Manager King Abdullah University Of Science And Technology
Depuis 7 années

A project is reporting negative cost variance, what is meant by this? ‎

A . Project is under budget B. Project is over budget C. The project is on budget D. None of the above‎

Réponses:
8
Adeptes:
Vues:
15
Vote Count:
4
La réponse doit contenir un minimum de 25 caractères.
Muhammad Farooq's image
La question a été ajoutée par Muhammad Farooq QA-QC MANAGER AL Bawani contracting co.
Depuis 6 années

A project manager reported the following Earned value data: PV: $12,400,000, EV: $14,500,000, AC: $14,500,000 ?‎

What does this mean? A. The project is under budget and on schedule. B. The project is on budget, but behind schedule. C. The project is on budget and ahead of schedule. ‎ ... Voir Plus

Réponses:
2
Adeptes:
Vues:
1532
Vote Count:
0
La réponse doit contenir un minimum de 25 caractères.
ZULFIQAR ALI's image
La question a été ajoutée par ZULFIQAR ALI Planning/ Project Control Manager King Abdullah University Of Science And Technology
Depuis 7 années

Earned Value Analysis is used to measure performance based on the following parameters?‎

A. Scope and Cost B. Scope and Schedule C. Scope, Cost and Schedule D. Cost and Schedule‎

Réponses:
3
Adeptes:
Vues:
76
Vote Count:
3
La réponse doit contenir un minimum de 25 caractères.
Muhammad Farooq's image
La question a été ajoutée par Muhammad Farooq QA-QC MANAGER AL Bawani contracting co.
Depuis 6 années

A junior project manager at your company does not know how to perform earned value analysis. You spend a weekend with him to teach him how ?‎

to do this. This is an example of: A. Fraternizing, and should be discouraged B. Unpaid overtime C. Giving access to proprietary information, and should be reported to PM‎ ... Voir Plus

Réponses:
2
Adeptes:
Vues:
301
Vote Count:
0
La réponse doit contenir un minimum de 25 caractères.
Tanveer Ahmad Niazi's image
La question a été ajoutée par Tanveer Ahmad Niazi CEO (Self-employed) Project Management Training & Consultant
Depuis 10 années
Réponses:
7
Adeptes:
Vues:
216
Vote Count:
9
La réponse doit contenir un minimum de 25 caractères.
Tanveer Ahmad Niazi's image
La question a été ajoutée par Tanveer Ahmad Niazi CEO (Self-employed) Project Management Training & Consultant
Depuis 10 années

What would be the best response if the Employer (Client) requests verbally for an additional work? Chose the options below and explain why?‎

Options -1. Accept that -2. Ask for a written request -3. Ask him to let you come back to him after getting feedback from management -4. Ask him to let you come back to h‎ ... Voir Plus

Réponses:
8
Adeptes:
Vues:
313
Vote Count:
9
La réponse doit contenir un minimum de 25 caractères.
Tanveer Ahmad Niazi's image
La question a été ajoutée par Tanveer Ahmad Niazi CEO (Self-employed) Project Management Training & Consultant
Depuis 11 années
Réponses:
4
Adeptes:
Vues:
159
Vote Count:
8
La réponse doit contenir un minimum de 25 caractères.
Muhammad Farooq's image
La question a été ajoutée par Muhammad Farooq QA-QC MANAGER AL Bawani contracting co.
Depuis 8 années
Réponses:
2
Adeptes:
Vues:
132
Vote Count:
1
La réponse doit contenir un minimum de 25 caractères.
Muhammad Farooq's image
La question a été ajoutée par Muhammad Farooq QA-QC MANAGER AL Bawani contracting co.
Depuis 8 années

You are three months into a six month project. Assume the budget burn rate is constant. The budget at...‎

completion (BAC) is $,. AC = $,. The SPI =1.2. What is the CPI of this project? (Round to2 decimal places) a.1. b.1. c.1. d. It cannot be determined from the informa‎ ... Voir Plus

Réponses:
4
Adeptes:
Vues:
1031
Vote Count:
1
La réponse doit contenir un minimum de 25 caractères.