Discussions Populaires Dans la Communauté Analyse de l annexe

S'abonner

Questionnez la Communauté


Ask any professional question and get answers from other specialists.

Stream language
Muhammad Farooq's image
La question a été ajoutée par Muhammad Farooq QA-QC MANAGER AL Bawani contracting co.
Depuis 6 années

You are managing a project with a total budget of $450,000. According to the schedule, your team should have completed 45% of the work by now.?‎

But at the latest status meeting, the team only reported that% of the work has actually been completed. The team has spent $, so far on the project. How would you BEST d‎ ... Voir Plus

Réponses:
8
Adeptes:
Vues:
48
Vote Count:
1
La réponse doit contenir un minimum de 25 caractères.
ZULFIQAR ALI's image
La question a été ajoutée par ZULFIQAR ALI Planning/ Project Control Manager King Abdullah University Of Science And Technology
Depuis 7 années
Réponses:
6
Adeptes:
Vues:
1918
Vote Count:
4
La réponse doit contenir un minimum de 25 caractères.
Tanveer Ahmad Niazi's image
La question a été ajoutée par Tanveer Ahmad Niazi CEO (Self-employed) Project Management Training & Consultant
Depuis 10 années

What is Schedule Analysis? ‎

The complex business relationships characteristic and technology advancements of the modern construction industry, construction scheduling has become increasingly more im‎ ... Voir Plus

Réponses:
10
Adeptes:
Vues:
554
Vote Count:
14
La réponse doit contenir un minimum de 25 caractères.
ZULFIQAR ALI's image
La question a été ajoutée par ZULFIQAR ALI Planning/ Project Control Manager King Abdullah University Of Science And Technology
Depuis 7 années
Réponses:
7
Adeptes:
Vues:
18
Vote Count:
3
La réponse doit contenir un minimum de 25 caractères.
ZULFIQAR ALI's image
La question a été ajoutée par ZULFIQAR ALI Planning/ Project Control Manager King Abdullah University Of Science And Technology
Depuis 7 années

Comparing target dates with the actual or forecast start and finish dates is called?‎

A. Variance Analysis B. Earned Value C. Progress Reporting D. Crashing‎

Réponses:
6
Adeptes:
Vues:
17
Vote Count:
4
La réponse doit contenir un minimum de 25 caractères.
Muhammad Farooq's image
La question a été ajoutée par Muhammad Farooq QA-QC MANAGER AL Bawani contracting co.
Depuis 6 années

Certain resources have been added to tasks on the critical path so as to reduce the project duration. As a result the plan should then be reviewed?‎

for the:  A. Possible lag time on other paths. B. Resource assigned to other tasks on the critical path. C. The most time consuming task remaining in the plan. D. Emerge‎ ... Voir Plus

Réponses:
7
Adeptes:
Vues:
28
Vote Count:
0
La réponse doit contenir un minimum de 25 caractères.
ZULFIQAR ALI's image
La question a été ajoutée par ZULFIQAR ALI Planning/ Project Control Manager King Abdullah University Of Science And Technology
Depuis 7 années
Réponses:
5
Adeptes:
Vues:
18
Vote Count:
3
La réponse doit contenir un minimum de 25 caractères.
Tanveer Ahmad Niazi's image
La question a été ajoutée par Tanveer Ahmad Niazi CEO (Self-employed) Project Management Training & Consultant
Depuis 10 années
Réponses:
7
Adeptes:
Vues:
216
Vote Count:
9
La réponse doit contenir un minimum de 25 caractères.
Binil Paul's image
La question a été ajoutée par Binil Paul Sr. Planning Engineer KEO International Consultants
Depuis 7 années
Réponses:
1
Adeptes:
Vues:
82
Vote Count:
1
La réponse doit contenir un minimum de 25 caractères.
Tanveer Ahmad Niazi's image
La question a été ajoutée par Tanveer Ahmad Niazi CEO (Self-employed) Project Management Training & Consultant
Depuis 10 années

What would be the best response if the Employer (Client) requests verbally for an additional work? Chose the options below and explain why?‎

Options -1. Accept that -2. Ask for a written request -3. Ask him to let you come back to him after getting feedback from management -4. Ask him to let you come back to h‎ ... Voir Plus

Réponses:
8
Adeptes:
Vues:
313
Vote Count:
9
La réponse doit contenir un minimum de 25 caractères.