Discussions Populaires Dans la Communauté Horaires

S'abonner

Questionnez la Communauté


Ask any professional question and get answers from other specialists.

Stream language
ZULFIQAR ALI's image
La question a été ajoutée par ZULFIQAR ALI Planning/ Project Control Manager King Abdullah University Of Science And Technology
Depuis 7 années

Comparing target dates with the actual or forecast start and finish dates is called?‎

A. Variance Analysis B. Earned Value C. Progress Reporting D. Crashing‎

Réponses:
6
Adeptes:
Vues:
17
Vote Count:
4
La réponse doit contenir un minimum de 25 caractères.
Muhammad Farooq's image
La question a été ajoutée par Muhammad Farooq QA-QC MANAGER AL Bawani contracting co.
Depuis 7 années

Resource reallocation from non critical to critical activities is an example of which Project Scheduling technique? ‎

  A. Critical Path Method B. Schedule Compression C. Resource Leveling D. What if Analysis  ‎

Réponses:
10
Adeptes:
Vues:
801
Vote Count:
1
La réponse doit contenir un minimum de 25 caractères.
Muhammad Yuseef's image
La question a été ajoutée par Muhammad Yuseef IT Manager Master Point Trading
Depuis 8 années
Réponses:
8
Adeptes:
Vues:
803
Vote Count:
2
La réponse doit contenir un minimum de 25 caractères.
مهرداد کتامی پور- مهرداد محمد جواد's image
La question a été ajoutée par مهرداد کتامی پور- مهرداد محمد جواد Project Planner Manager Omrab Engineering Co
Depuis 8 années
Réponses:
3
Adeptes:
Vues:
118
Vote Count:
2
La réponse doit contenir un minimum de 25 caractères.
Muhammad Farooq's image
La question a été ajoutée par Muhammad Farooq QA-QC MANAGER AL Bawani contracting co.
Depuis 8 années

The customer has demanded that you reduce the schedule by three weeks. What does this mean in terms of the Project schedule?‎

a. You have decided that fast tracking is the best option to pull in the schedule by three weeks b. You have decided that crashing the schedule is the best option to pul‎ ... Voir Plus

Réponses:
7
Adeptes:
Vues:
1367
Vote Count:
1
La réponse doit contenir un minimum de 25 caractères.
Muhammad Farooq's image
La question a été ajoutée par Muhammad Farooq QA-QC MANAGER AL Bawani contracting co.
Depuis 8 années
Réponses:
5
Adeptes:
Vues:
643
Vote Count:
1
La réponse doit contenir un minimum de 25 caractères.
Muhammad Farooq's image
La question a été ajoutée par Muhammad Farooq QA-QC MANAGER AL Bawani contracting co.
Depuis 8 années

Management from the customer side wants to bring in a project one month earlier than they had...‎

originally planned. Based on the current project timeline, product testing will have to be cut short. You have reviewed several options with the customer; they have decid‎ ... Voir Plus

Réponses:
3
Adeptes:
Vues:
266
Vote Count:
1
La réponse doit contenir un minimum de 25 caractères.
Muhammad Farooq's image
La question a été ajoutée par Muhammad Farooq QA-QC MANAGER AL Bawani contracting co.
Depuis 7 années

You are project manager for a project. This project was originally scheduled for completion in 1 year but already 2 years over and now also project?‎

 is in execution phase. Which statement is TRUE about the project?  A. requirement added later therefore project is running late B. temporary project C. key resource h‎ ... Voir Plus

Réponses:
7
Adeptes:
Vues:
14
Vote Count:
0
La réponse doit contenir un minimum de 25 caractères.
Muhammad Farooq's image
La question a été ajoutée par Muhammad Farooq QA-QC MANAGER AL Bawani contracting co.
Depuis 8 années

Which of the following statements are TRUE regarding various Activity Scheduling tools?‎

A. PDM allows for conditional branching and iteration of activitiesB. PDM uses activity-on-node (AON) diagramming method.C. PDM allows for conditional branching and itera‎ ... Voir Plus

Réponses:
4
Adeptes:
Vues:
646
Vote Count:
0
La réponse doit contenir un minimum de 25 caractères.
Muhammad Farooq's image
La question a été ajoutée par Muhammad Farooq QA-QC MANAGER AL Bawani contracting co.
Depuis 8 années

CPI is 1.2, SPI is 1.1. Four months later CPI is.91 and SPI is .86. The most likely reason for this change is?‎

  a. The project manager has not been keeping track of variances on the project to implement corrections b. As work packages were being executed, discovery on critical ‎ ... Voir Plus

Réponses:
7
Adeptes:
Vues:
365
Vote Count:
0
La réponse doit contenir un minimum de 25 caractères.