Communiquez avec les autres et partagez vos connaissances professionnelles

Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.

Suivre

Earned value = 650, planned value = 550, actual cost = 700. What is the SV at this point in time? a. + 100 , b. – 50, c. – 100, d. – 150 ?

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2016/05/17
Mohamed Helal
par Mohamed Helal , Project Manager , GROUP CONSULT INTERNATIONAL

a. + 100

Schedule Variance = Earned Value – Planned Value

SV = EV – PV

sardar mardookhy
par sardar mardookhy , Head of portfolio management department , MCI

Agreed with answers A option

Eng Ahmed Elsharkawy
par Eng Ahmed Elsharkawy , Civil Engineering Project Manager , Altwijry office

thanks for invition ,,,,,,,,,, my choice is option A

I apologize for the answer I leave the answer to the specialists the experts in the this field that's not my area.

More Questions Like This